Construction continues on Signature Blvd in Hazelwood

Date posted: October 14, 2016

img_8191Progression being made at Almono Site

Since it's Groundbreaking a year ago, Signature Boulevard at Almono has made significant headway-approximately 75% completed- and is looking good to being finished on-time.

As of now, 90% of the utilities have been installed, along with street curbs, road sub-base and storm water management facilities.

In Springtime, the paving wearing course and final landscaping will all be done. img_8190

Everyone looks forward to it's completion as the first of many projects at the site!